Managing Projects with Microsoft Project 2013

Question No: 61

You are managing a project by using Project Professional 2013.

Your project schedule contains 1000 tasks which are in outline format. You discover that the Design summary task is located below the Build summary group of tasks.

You need to move the Design summary task and its detail tasks to the proper location. What should you do?

  1. Click on the Design summary task name and drag it above the Build group of tasks.

  2. Make the Design summary task grouping a manual task, and drag the Design task name above the Build group of tasks.

  3. Cut all of the tasks below the Design summary task and paste them above the Build group of tasks.

  4. Click on the ID number for the Design summary task grouping and drag the group above the Build group of tasks.

Answer: D

Question No: 62

You are a project manager and have built a project plan by using Project Professional 2013.

Your project plan has both fixed duration and fixed work tasks.

You have been asked to denote key existing tasks as milestones in the Gantt view. What should you do?

  1. Format the bar styles in the Gantt view to denote the tasks as milestones.

  2. Enter the word Milestone in the Task Duration column to set the task as a milestone.

  3. Set the Duration column to 0 to set the task as a milestone.

  4. Navigate to View, Text Styles, select Milestones, and then select the black diamond.

Answer: C

Question No: 63

You are project manager who uses Project Professional 2013.

Your organization uses Microsoft SharePoint 2013 and uses a SharePoint task list to define the tasks required on an upcoming project. The task list contains over 100 items.

You need to create a project based on the tasks in the SharePoint list in the most efficient manner.

What should you do?

  1. Export the tasks into Microsoft Excel and then import the Excel file into Project Professional 2013.

  2. Edit the Project Summary Task hyperlink column to point to the SharePoint task list and click the Import button.

  3. Open the tasks directly from the SharePoint site into Project Professional 2013.

  4. Copy and paste the tasks from SharePoint into Project Professional 2013.

Answer: C

Question No: 64

Your company uses Project Standard 2013 to track project progress.

You need to accurately calculate cost performance index (CPI) as a health indicator.

Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)

  1. Ensure there is a value in the Status Date field.

  2. Ensure there is a value in the Standard Rate field.

  3. Ensure Task Dependencies exist in the schedule.

  4. Enter actual progress information.

  5. Level resources within available slack.

Answer: A,B,D

Question No: 65

You are a project manager who uses Project Professional 2013.

A customer has sent you a project plan, which contains several custom fields that you want to use in your project. You have a custom field named CF1 in the Number1 field in your project, and you have a custom field named CF2 in the Number1 field of your customer#39;s project.

You need to copy the custom fields from your customer#39;s project into your own. You do not want to overwrite your project custom field.

You open both projects. What should you do next?

  1. Use the Organizer to move the custom fields from one project to the other.

  2. Cut and paste the custom fields from one project to the other.

  3. Drag the custom fields from one project to the other.

  4. Open the custom fields dialog box and use the Import Fields button.

Answer: D

Question No: 66

You manage a project for an organization that uses Project Professional 2013.

You reset the baseline for some selected tasks. After the baseline has been updated with the new values, you realize that some of the summary baseline duration values are not correct.

You need to resolve this problem. What should you do?

  1. Update the summary tasks manually with the new duration values.

  2. Change all task durations to the same denomination values, such as days, weeks, or months.

  3. Reset the baseline for the selected tasks and select the Roll up baselines to all summary tasks option.

  4. Reset the summary tasks to manual scheduling.

Answer: C

Question No: 67

You are a program manager who uses Project Professional 2013.

You manage a portfolio of projects for a large point of sale implementation. All of your project managers have created individual project schedules. You discover that you have resource constraints since multiple resources are working on multiple projects.

You need visibility into resources across all projects so that you can most efficiently manage the resources and their availability.

What should you do?

  1. Create a shared resource pool and send the location to each project manager. Open the individual project and the resource pool. From the individual project, select Resource Pool, Share Resources, and choose Use Resources.

  2. Create a shared resource pool and send the location to each Project Manager. Open the individual project, select Resource Pool, Share Resources, and choose Use Resources.

  3. Create a master resource list and send it to each project manager. Open the individual project and copy and paste it into the Resource Sheet.

  4. Create a master resource list and send it to each project manager. Open the individual project, select Team Planner, and add the resources.

Answer: A

Question No: 68

Your organization uses Microsoft Project 2013.

You are finalizing the Project Schedule for a very complex project with over 100 resources. You need to ensure that all tasks are assigned to resources.

What should you do?

  1. Use Task Usage view and look for Unassigned tasks.

  2. Use Resource Graph view and look for the Unassigned resource name.

  3. Use Resource Usage view and look for the Unassigned resource name.

  4. Use Resource Sheet view and look for Unassigned tasks.

Answer: C

Question No: 69

You are a project manager, and your organization uses Project Professional 2013.

You have created a detailed project schedule and have identified two tasks that are causing your resource to be overallocated.

You need to use the Team Planner to reassign these tasks from the overallocated resources to underallocated resources with the same skill set.

What should you do?

  1. Right-click the task and reassign it to the underallocated resource.

  2. Drag the underallocated resource on the task to reassign it.

  3. Drag one of the tasks from the overallocated resource to the Unassigned Tasks section.

  4. Right-click the resource and reassign it to the underallocated resource.

Answer: A

Question No: 70

You are a project manager who uses Project Standard 2013.

You are creating a preliminary project schedule and are estimating the number of

resources required prior to finalizing the schedule. You do not have named resources to complete the tasks, but you know the resource roles that are necessary. One of the roles needed is architect.

You need to estimate how many architect hours are required to complete the work. What should you do?

  1. Add a Material Resource named architect.

  2. Add a Budget Resource named architect.

  3. Add a Work Resource named architect,

  4. Add a Cost Resource named architect.

Answer: C

100% Free Download!
Download Free Demo:74-697 Demo PDF
100% Pass Guaranteed!
Download 2017 EnsurePass 74-697 Full Exam PDF and VCE

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 EnsurePass IT Certification PDF and VCE

[Free] 2017(Sep) EnsurePass Testking Microsoft 74-697 Dumps with VCE and PDF 51-60

EnsurePass
2017 Sep Microsoft Official New Released 74-697
100% Free Download! 100% Pass Guaranteed!
http://www.EnsurePass.com/74-697.html

Managing Projects with Microsoft Project 2013

Question No: 51

You are a project manager who uses Project Professional 2013.

When viewing the critical path, you notice that there are some inconsistencies. To investigate the status of the critical path, you insert the Total Slack column into a task table. You discover that many of the tasks have negative Total Slack values.

You need to resolve the negative Total Slack values. What should you do?

  1. Remove lag time from task relationships.

  2. Remove as many constraints as possible.

  3. Re-assign resources that have more availability at the time of the negative slack.

  4. Remove lead time from the task relationships.

Answer: B

Question No: 52

You are a project manager who uses Project Professional 2013.

You are planning an office move, which will occur over a weekend. You use Auto Scheduled tasks and create a weekend working calendar.

You need to assign the weekend working calendar to the task. What should you do?

  1. Change the start date of the task to the Saturday, which will assign the weekend working calendar to the task.

  2. Click on the Task tab and select the Change Working Time button. Assign the weekend working calendar to the task.

  3. Assign the task calendar to the task using the Task Information dialog box.

  4. Right-click on the weekend on the Gantt chart and select the weekend working calendar.

Answer: C

Question No: 53

Your company uses Project Professional 2013.

An organization with project managers of varying expertise wants a simple, standard view that displays overall project status.

You need an out-of-box function that provides the ability to assess current, baseline, and actual work for the project.

Which view should you use?

  1. Project Overview dashboard

  2. Resource Allocation view

  3. Work Overview dashboard

  4. Relationship Diagram view

Answer: C

Question No: 54

Your company uses Project Professional 2013.

You are setting up a preliminary schedule by using manually scheduled tasks. You create a task with no duration, start, or finish date, and then you assign a resource. Later, you enter a duration of three days for that task.

You need to let the resource know how the Work will be affected. What should you say?

  1. Work will increase to 24 hours.

  2. Work will remain at 0 hours.

  3. Work will increase to 16 hours.

  4. Work will remain at 8 hours.

Answer: A

Question No: 55

You are a project manager who uses Project Standard 2013. You have been told to build multiple project files for a program.

You need to have all of your projects start with auto scheduled tasks by default. What should you do?

  1. Under schedule options, set New tasks created to Auto Scheduled for each project.

  2. Use the Task Mode field to change the first task to Auto Schedule, then copy down for all of your tasks.

  3. Under schedule options, set New tasks created to Auto Scheduled for all new projects.

  4. Highlight all of the tasks in your schedule and select the Auto Schedule button.

Answer: C

Question No: 56

You are an independent project manager who uses Project Professional 2013.

You work in multiple projects for different customers and use one project to manage all their tasks. You create a custom field called Customer Name to identify the customer, and you use the Cost field to monitor the amount of money for each task.

You need to view the most expensive detail tasks in the top of your table without subtotals and summaries.

You turned off summary tasks. What should you do next?

  1. Set the Sort by option to Cost Descending.

  2. Create a custom group based on Cost and Customer Name fields. Define a group by Cost with order as ascending.

  3. Set the Sort by option to Cost Ascending.

  4. Create a custom view based on Cost and Customer Name fields. Define a group by Cost with order as descending.

Answer: A

Question No: 57

Your organization uses Project Professional 2013.

A senior stakeholder informs you that your project start date is delayed and gives you a new start date.

You need to change the project start date without adding constraints.

What are three possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose three.)

  1. Modify the Start Date field in project information to the new date.

  2. Use Move Project to move the project to the new start date.

  3. Enter the new start date for all tasks without predecessors.

  4. Use Update Project and set a new start date.

  5. Set a new project status date and then set the baseline.

Answer: A,B,C

Question No: 58

You manage a project by using Project Professional 2013.

The work variance for a task is 48 hours. The remaining work is 25 hours. The work for this task has been completed.

You need the work variance to be adjusted to reflect what has occurred during the performance of the task.

What should you do?

  1. Adjust the value in the Baseline Work column.

  2. Enter a 0 in the remaining Duration column.

  3. Adjust the value in the Work Variance column.

  4. Mark the task inactive.

Answer: B

Question No: 59

You are a project manager who uses Project Standard 2013, and your task list includes a

flag field that indicates, with Yes or No, if a non-summary task represents a physical deliverable.

Your project involves several tasks marked as deliverables, and management requires you to track how many deliverables are completed. The deliverable is considered completed when the Percent complete field is 100%.

You need to create a formula to calculate the total number of deliverables that are completed.

Which two steps should you perform? (Each correct answer presents part of the solution. Choose two.)

  1. Use the following formula: IIf([Physical Deliverable]=Yes And [% Complete]=100,1,0).

  2. Set Calculation for tasks and summary groups to Sum.

  3. Use the following formula: IIf([Physical Deliverable]=Yes And [% Complete]=100,0,1).

  4. Set Calculation for tasks and summary groups to Count All.

Answer: A,B

Question No: 60

Your company uses Project Professional 2013.

You have two projects, Project 1 and Project 2, as well as a resource pool to contain all of the resources. You use resource leveling and want to prioritize the projects so that Project 1 is the highest priority project and gets all the required resource availability first. Project 2 then gets resources as they become available from Project 1.

You need to maintain this priority throughout the execution of the project. What should you do?

  1. Set resource leveling to prioritize by project, priority, and standard.

  2. Make sure the resource pool is configured to list Project 1 first.

  3. Level Project 1 first, and then level Project 2.

  4. Set Project Priority higher for Project 1, and then set resource leveling to level by priority, standard.

Answer: D

100% Free Download!
Download Free Demo:74-697 Demo PDF
100% Pass Guaranteed!
Download 2017 EnsurePass 74-697 Full Exam PDF and VCE

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 EnsurePass IT Certification PDF and VCE

[Free] 2017(Sep) EnsurePass Testking Microsoft 74-697 Dumps with VCE and PDF 41-50

EnsurePass
2017 Sep Microsoft Official New Released 74-697
100% Free Download! 100% Pass Guaranteed!
http://www.EnsurePass.com/74-697.html

Managing Projects with Microsoft Project 2013

Question No: 41

You are managing a project using Project Professional 2013.

Your project schedule is showing task overallocation indicators in the Gantt chart view. You navigate to the Team Planner view to investigate more details regarding the over allocations.

You discover that the BA1 resource is overallocated and you need to see all assignments with details for BA1 to understand their current workload before making any assignment changes.

What should you do?

  1. Click the BA1 resource and scroll to the end of the project.

  2. Click View, check Details, select Resource Form then click on the BA1 resource.

  3. Click View, check Details, select Task Form then click on the BA1 resource.

  4. Right-click the BA1 resource and select Information.

Answer: B

Question No: 42

You are a project manager, and you successfully complete a server consolidation project for one of your data centers. You use Project Standard 2013 to plan and track the work.

Your manager wants you to begin similar projects on two other data centers. You need to create a template based on the plan you used to manage the first data center consolidation project.

You need to ensure that the template has all baseline and actual data values removed. What should you do?

  1. Within Microsoft Windows Explorer, create a copy of the original project plan and rename the file type from .mpp to .mpt.

  2. Open the plan and use the Move Project button to set the start date to the start of the new project. Save the project file as Template.mpp.

  3. Open the plan and reset the percent complete for each task to 0. Save the file as Template.mpp.

  4. Open the plan and save the plan as a Project Template.

  5. Open the plan, and copy and paste all of the task information into a new plan. Save the plan as a Project Template.

Answer: D

Question No: 43

You manage a project by using Project Professional 2013. Your project is updated with changes to the baseline for selected tasks.

You back up your project fife before you start your next tracking cycle. After completing the tracking cycle, you notice that the baseline duration values on some of the summary tasks are not correct.

You need to correct these values before re-entering the tracking data. You open the backed up version of the project schedule.

What should you do next?

  1. Manually update the summary tasks with the new duration values.

  2. Reset the summary tasks to manual scheduling.

  3. Ensure the tasks durations are of the same denomination values. Then reenter the tracking data.

  4. Reset the baseline checking the Roll up baselines to all summary tasks option. Then reenter the tracking data.

Answer: D

Question No: 44

You are a project manager who uses Microsoft Excel 2013.

Your company decides to migrate all of the current projects in Microsoft Excel 2013 to Project Professional 2013. They allow all employees to spend 8 hours migrating each project plan. Your current and unique project plan has 462 tasks with duration in days, and resources have been assigned and named. You have a status meeting in two days.

You need to provide your project#39;s information by using Project Professional 2013. What should you do?

  1. Create a new project plan in Project Professional 2013 and use the Gantt Chart Wizard to import from an Excel Workbook.

  2. Rename the Excel file from .xlsx to .mpx, and open it by using Project Professional 2013, activating the Mapping Excel Workbook feature. Map tasks, durations, and resources assigned into Microsoft Project fields.

  3. Open the Excel File .xlsx directly from Project Professional 2013, which will convert and map tasks, durations, and resources assigned into Project fields.

  4. Create a VBA macro by using the Excel Record Macro feature to import all tasks, durations, and resources assigned from Excel into your new Project Professional 2013 project plan.

Answer: C

Question No: 45

You are a project manager, and your company uses Project Professional 2013. You are setting up a preliminary schedule by using manually scheduled tasks.

You create two manually scheduled tasks and link them in a Finish to Start relationship. The project team member asks you to increase the duration of the predecessor task.

You notice that the successor task start date is now before the finish date of the predecessor task.

You want the successor task to start after the predecessor finishes. What should you do?

  1. Select both tasks and click Unlink.

  2. Select the successor task and click Mark on Track.

  3. Select the predecessor task and click Respect Links.

  4. Select the successor task and click Respect Links.

Answer: D

Question No: 46

You are a senior project manager, and your organization uses Project Standard 2013.

You are managing a large ERP project with both part-time and full-time resources. The part-time resources have strict contractual limitations regarding working days and hourly availability.

You need to make sure the tasks for your part-time resources are only scheduled in the calendar during their agreed-upon working days and hours.

What should you do?

  1. Change the part-time resources#39; tasks to manually scheduled to ensure the dates do not go past the agreed-upon terms of their contract.

  2. Enter the availability start and end dates for each resource and change the percent of units to the agreed-upon amount in their contract.

  3. Enter the availability start and end dates for each resource and change the working time for each resource to only include days and hours agreed upon in their contract.

  4. Change the part-time resources#39; units to the percentage they are available and set task constraints to must finish on to ensure the dates do not go past the agreed-upon terms of their contract.

Answer: C

Question No: 47

You are a project manager for a company that uses baselines in Project Standard 2013.

Project stakeholders approve an update to the baseline of a project in progress. You enter the new tasks necessary to include the project schedule changes.

You need to update the baseline for the new tasks. What should you do?

  1. Delete the current baseline and re-baseline the entire project.

  2. Copy the current schedule to the baseline1 fields.

  3. Select the new tasks and copy the schedule to the baseline1 fields for the selected tasks.

  4. Select the new tasks and set the baseline for the selected tasks.

Answer: D

Question No: 48

You are a project manager for a software development company that uses Project Professional 2013.

For managing projects, your company has its own specialized processes, all of which you are familiar with, except for the reporting processes. Additionally, your company#39;s status reports of project progress are based on Work and Cumulative Work.

Thirty minutes before a meeting is scheduled to begin, the president of your company asks you to present the status report at the meeting.

You need the report to show all project tasks, resources assigned, and their respective Work and Cumulative Work on a monthly basis.

What should you do?

  1. Select the Gantt Chart view that has all project tasks and resources assigned. Click Add New Column to add Work and Cumulative Work. Go to the Gantt chart and adjust the timescale by zooming in or out to fit the monthly basis.

  2. Select the Gantt Chart view that has all project tasks and resources assigned. Right- click on the Gantt chart, selecting Work and Cumulative Work. Adjust the timescale by zooming in or out to fit the monthly basis.

  3. Select the Task Usage view that has all project tasks and resources assigned. Right- click the Details table, selecting Work and Cumulative Work. Adjust the timescale by zooming in or out to fit the monthly basis.

  4. Select the Network Diagram View. Choose Format Box Styles and add Cumulative Work to the Critical Task Box style.

Answer: C

Question No: 49

While creating a schedule with Project Professional 2013, you notice that there is a three- day duration on the Database Design task.

After working for only two days, the resource performing the task reports two days of work and notifies you that the task is finished.

You need to update the schedule with this information. What should you do?

  1. Reschedule uncompleted work for the project schedule.

  2. Add two days of actual duration and change the remaining duration for the task to zero.

  3. Update the task to show 100% completion on the ribbon bar.

  4. Enter a status date for the task.

Answer: B

Question No: 50

Your organization uses Project Professional 2013 and records actual hours worked on the project.

You manage a small e-commerce website implementation project. One of your testers asks for assistance in completing a critical task, and you find two additional testing resources that can assist with executing the critical test cases.

The total estimated work for the effort-driven task is 100 hours. The original testing resource, Resource1, completes 25 hours of work on the task.

You need to add Resource2 and Resource3 to the task and split the remaining hours across all three resources now working on the task.

Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

  1. Open the Task Form and format it to show Work Details. Enter 25 hours of actual work for Resource1. Then save the changes.

  2. Open the Task Form and format it to show Work Details. Enter 75 hours of remaining work for the assigned resource. Then save the changes.

  3. Assign Resource2 and Resource3 to the task. Then save the changes.

  4. Open the Task Form and format it to show Work Details. Enter 33.33 hours of work for each resource. Then save the changes.

Answer: A,C

100% Free Download!
Download Free Demo:74-697 Demo PDF
100% Pass Guaranteed!
Download 2017 EnsurePass 74-697 Full Exam PDF and VCE

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 EnsurePass IT Certification PDF and VCE

[Free] 2017(Sep) EnsurePass Testking Microsoft 74-697 Dumps with VCE and PDF 31-40

EnsurePass
2017 Sep Microsoft Official New Released 74-697
100% Free Download! 100% Pass Guaranteed!
http://www.EnsurePass.com/74-697.html

Managing Projects with Microsoft Project 2013

Question No: 31

You are a project manager who uses Project Professional 2013.

You work on a construction project that requires propane as a fuel source for your equipment. The foreman requires that you enter project costs associated with all work completed on your project.

The propane costs $5.00 per gallon, and the tank holds 500 gallons of propane. Each time the tank is refilled, you must pay a fee of $20.

You need to enter the propane costs into your project schedule prior to filling the propane tank for the first time.

What should you do?

  1. Create a material resource with a material label of gallons. Enter $20 in the cost per use and $5.00 in the standard rate.

  2. Create a cost resource, add the resource to a task, and enter $25 in the actual cost.

  3. Create a material resource with a material label of gallons. Enter $20 in the standard rate and $5.00 in the cost per use.

  4. Create a cost resource, add the resource to a task, and enter $2520 in the actual cost.

Answer: B

Question No: 32 DRAG DROP

You are a project manager who uses Project Standard 2013.

Your project is approved, and you identify named resources to replace the generic resources for your project tasks.

You need to update the project schedule to assign the named resources to their appropriate tasks.

Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.)

Ensurepass 2017 PDF and VCE

Answer:

Ensurepass 2017 PDF and VCE

Explanation:

Box 1:

Ensurepass 2017 PDF and VCE

Box 2:

Ensurepass 2017 PDF and VCE

Box 3:

Ensurepass 2017 PDF and VCE

Note:

  1. On the Resource tab, in the Assignments group, click Assign Resources.

    The Assign Resources dialog box appears, in which you see the resource names you earlier (step 1), plus additional resources.

  2. In the Task Name column in the Gantt Chart view, select the task.

  1. In the Resource Name column in the Assign Resources dialog box, click the name of the assigned resource, and then click Replace (not Assign as we already have a dummy/generic assignment).

    Question No: 33

    You use Project Professional 2013 to manage a project schedule which includes all task relationships.

    The resource who is assigned to the quot;Develop software deliveryquot; task is no longer available to work on your project. You can find another resource to perform this task, but you are not sure when the resource will become available.

    You need to know which future tasks could be affected as a result of the resource leaving your project.

    What should you do?

    1. Sort all tasks by start date and check start dates of tasks that are scheduled after the Develop Software Delivery task.

    2. View the critical path for tasks that are successors to the Develop Software Delivery task.

    3. View the Network diagram and filter for the predecessor tasks to Develop Software Delivery task.

    4. Use the Task path function to check driven successors for the Develop Software Delivery task.

Answer: D

Question No: 34

You are a project manager for a software development company. You use Project Professional 2013.

You manage an integration project, and you discover that you need to add additional resources to the integration tasks in order to meet your development complete milestone date. The project is behind schedule, so you must shorten the duration of the integration development work.

You identify two additional resources to work on the integration task. When you add these resources, your task now shows it will complete three days ahead of schedule, which leaves a contingency window for issues that may arise.

In order to shorten the duration of the task when the resources are added, you need to set the task type before adding the resources.

What should you do?

  1. Use an automatically scheduled task and set the task type to fixed duration.

  2. Use a manually scheduled task and set the task type to fixed work.

  3. Use an automatically scheduled task and set the task type to fixed work.

  4. Use a manually scheduled task and set the task type to fixed duration.

Answer: C

Question No: 35

You are a Project Manager who uses Project Professional 2013.

You manage a critical project, which is synchronized with a Microsoft SharePoint Task List.

One of your team members has changed a task priority to High in SharePoint, and you do not see the changed data in Project Professional 2013.

What should you do?

  1. Use the Organizer to copy the Priority field from the SharePoint Task List.

  2. Map the Priority field from SharePoint to Project by using File, Info.

  3. Map the Priority field from SharePoint to Project by using Project, Custom Fields, Import Field.

  4. Use the Task Information box to copy the Priority field from the SharePoint Task List.

Answer: B

Question No: 36

Your company uses Project Professional 2013.

You are scheduling two tasks. One task is named Test Solution, and the other task is named Create Solution Test Plan. You want the Test Solution task to start three working days after the finish date of the Create Solution Test Plan task.

You need to set up a dependency between these two tasks. What should you do?

  1. Create a Start to Start predecessor relationship from the Create Solution Test Plan task to the Test Solution task. Set a lead time of three days.

  2. Create a Start to Start predecessor relationship from the Test Solution task to the Create Solution Test Plan task. Set a lead time of three days.

  3. Create a Finish to Start predecessor relationship from the Test Solution task to the Create Solution Test Plan task. Set a lag time of three days.

  4. Create a Finish to Start predecessor relationship from the Create Solution Test Plan task to the Test Solution task. Set a lag time of three days.

Answer: D

Question No: 37

Your company uses Project Professional 2013. You are a program manager who has a master project created for your program.

Currently you are seeing the critical path for each independent project in the master project. As a program manager, you want to ensure the resources are properly applied to successfully complete the program.

You need to display the critical path for the entire program instead of each independent project.

What should you do?

  1. Turn on Inserted projects are calculated like summary tasks in the Schedule section of Project Options.

  2. Turn on Calculate multiple critical paths in the Advanced section of Project Options.

  3. Insert the Critical field, and change the values to Yes for the non-critical tasks.

  4. Double-click the inserted project summary task and uncheck Roll Up.

Answer: A

Question No: 38

You are a program manager for a complex software development project. You use Project Professional 2013 to manage your project. Your resources work on many different projects across the program, and you need to resolve resource over allocations. Your project team uses a resource pool to manage resources.

Resource1 has been assigned to assist on a project that is on the critical path. After assigning Resource2 to the task, you notice that Resource1 is over allocated during the month of November. Project A, which is on critical path, takes priority over Project B, which Resource1 is also assigned to.

Using resource leveling in Project Professional 2013, you need to resolve the over allocation for Resource1 for the month of November only.

What should you do?

  1. Set the priority of Project A to 1000 and the priority of Project B to 500, Set the Leveling Range for November. Change the leveling order to Priority, Standard. Select Level Resource, and choose Resource1 and Level Now.

  2. Set the priority of Project A to 500 and the priority of Project B to 1000. Set the Leveling Range for November. Change the leveling order to Standard and select Level Resource. Then choose Resource1 and Level Now.

  3. Set the priority of Project A to 1000 and the priority of Project B to 500. Change the leveling order to Standard, and select Level All.

  4. Set the priority of Project A to 500 and the priority of Project B to 1000. Change the leveling order to Priority, Standard, and select Level All.

Answer: A

Question No: 39

You are using Project Standard 2013.

Management wants to see an overview of your project that shows the overall start and finish dates, total duration, and the name of the project. They want to see this information in a simple layout that does not include task details.

You need to show one line item that displays all the requested information in the Gantt view.

What should you do?

  1. Apply the Top Level Tasks filter.

  2. On the format ribbon, check the box next to Project Summary Task.

  3. Apply the default Summary Tasks filter.

  4. On the format ribbon, check the box next to Summary Tasks.

Answer: D

Question No: 40

You are a project manager, and your organization uses Project Standard 2013.

You have created a non-working day in a resource#39;s calendar; however, the HR department notifies you that the resource will work that day after all.

You need to reflect this change in the project in the most efficient manner. What should you do?

  1. Open the Project calendar and mark the work day as working.

  2. Open the resource#39;s working calendar and edit the Work Week details to set the day as working.

  3. Open the resource#39;s working calendar and delete the exception.

  4. Open the resource#39;s working calendar and mark the day as working.

Answer: C

100% Free Download!
Download Free Demo:74-697 Demo PDF
100% Pass Guaranteed!
Download 2017 EnsurePass 74-697 Full Exam PDF and VCE

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 EnsurePass IT Certification PDF and VCE

[Free] 2017(Sep) EnsurePass Testking Microsoft 74-697 Dumps with VCE and PDF 21-30

EnsurePass
2017 Sep Microsoft Official New Released 74-697
100% Free Download! 100% Pass Guaranteed!
http://www.EnsurePass.com/74-697.html

Managing Projects with Microsoft Project 2013

Question No: 21

You work as a project manager for a construction company that uses Project Professional 2013.

You have created your work breakdown structure (WBS) and are adding resources to your tasks. However, one of your tasks requires multiple resources. You have the name of the project#39;s lead support individual, and you have been provided with the equivalent of three full-time support resources. These three resources are not named individuals but are part of a group.

The actual individuals from this group will change based on coverage schedules. The resources have the following cost structures:

  • The lead is billed out at S175/hour.

  • The group resources are billed out at $140/hour.

You need to add these resources to the schedule and track your project costs.

Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

  1. Add the named resource to the task with an allocation of 100% and a standard rate of

    $175/hour.

  2. Add the named resource to the task with an allocation of 400% and a standard rate of

    $157.50/hour.

  3. Add the group resource to the task with an allocation of 300% and a standard rate of

    $140/hour.

  4. Add the group resource to the task with an allocation of 100% and a standard rate of

$l40/hour.

Answer: A,C

Question No: 22

You are a project manager for an organization that uses Project Standard 2013.

You add shortcuts on the Quick Access Toolbar to your most frequently used commands.

Your manager is impressed with the ease of use this customization provides and would like other project managers in the group to use it.

You need to deploy the customization to these project managers. What should you do?

  1. Save a Project File with the customizations to the ribbon in the file. Ask the other project managers to open the file.

  2. Email your global.mpt file to each project manager. Ask them to place the template in the %appdata%\Microsoft\MS Project\15 \1033 folder.

  3. Click on the Import/Export button to export the customizations to a file. Ask the other project managers to import the file.

  4. Use regedit to export the following key: HKLM\Software\Microsoft\Office\15.0\User Settings\ProjectRibbon. Ask the other project managers to import the key.

Answer: C

Question No: 23

Your organization uses Project Professional 2013.

You are setting up a preliminary schedule by using manually scheduled tasks.

As you build the task breakdown, you notice a potential scheduling problem indicated by a wavy red line under the finish date of a detail task.

You need to determine the cause of the wavy red line. What should you do?

  1. Evaluate the task to determine if there is a deadline.

  2. Insert the Constraint Type field and view the task constraints.

  3. Evaluate the task by using the Task Inspector.

  4. View the Resource Sheet to see if you have overallocated resources.

Answer: C

Question No: 24

You are an independent project manager who uses Project Professional 2013.

You work on multiple projects for different customers, and you use one project to manage all of their tasks. You invoice your customers on a monthly basis.

You use a custom field named Not Invoiced to identify all tasks that have not been invoiced, and you use a custom field named Customer Name to identify the customer.

You need to see all tasks that have not been invoiced, but only for one customer at a time. What should you do?

  1. Group by the Not Invoiced field and display the AutoFilter for the Customer name column.

  2. Group by Customer name and display the AutoFilter for the Not Invoiced column.

  3. Display the AutoFilter and apply it for the Customer Name and the Not Invoiced columns.

  4. Create a custom highlight filter that asks for a Customer name value and identifies Not Invoiced tasks.

Answer: C

Question No: 25 DRAG DROP

You are a senior project manager in a software development company. You manage your projects with Project Professional 2013.

The development team is behind schedule due to a problem found in the architectural design of the database. The lead architect estimates that redesigning the database will take approximately 30 hours. You create a new manual task and assign it to the lead architect. However, the task has not been scheduled.

You need to easily see a time phased view of all tasks for the lead architect in order to schedule the task for completion.

Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.)

Ensurepass 2017 PDF and VCE

Answer:

Ensurepass 2017 PDF and VCE

Explanation:

Box 1: Go to the Team Planner and locate the Lead Architect resource. Box 2: Select the unscheduled Database Redesign task.

Box 3: Drag the Database Redesign task to the date grid to schedule the work.

Note:

* The Team Planner is a new view in Project 2010 that shows a Gantt Chart-like view of assignments per resource.

Question No: 26

You are a project manager who uses Project Professional 2013.

You manage a critical project, which involves many team members. You are the only team member who has Project Professional 2013. You need to receive updates from team members directly from Microsoft SharePoint without having to reenter the updates in your project.

What should you do?

  1. Set up your project to sync with a SharePoint Task List.

  2. Save your project as an mpp file to a SharePoint Shared Documents library.

  3. Copy and paste all tasks into a Microsoft Excel file saved in SharePoint.

  4. Copy and paste all tasks into a new SharePoint Task List.

Answer: A

Question No: 27

Your organization uses Project Professional 2013 and Microsoft SharePoint 2013.

You are responsible for a project with resources in different offices. All offices share the same SharePoint intranet, and all resources have valid accounts to log into the company intranet. Your project plan already has the correct names and assignments for each resource involved in this project.

You need to share and receive project plan updates dynamically with your resources. What should you do?

  1. Sync with SharePoint Tasks List, automatically creating a Project Site synchronized to your Project Plan.

  2. Create the Project Site in SharePoint and upload the project plan to the project site.

  3. Create the Project Site in SharePoint and save the project plan to the project site.

  4. Copy and paste the project tasks to a SharePoint task list.

Answer: A

Question No: 28

You are a manager for an organization that uses Project Professional 2013.

A critical project shows average finish variance values between 5-10 days for the tasks. You need to interpret these variance values to determine the next course of action to take. What do these variance values mean?

  1. The project is on schedule.

  2. The project is running between 5-10 days ahead of schedule.

  3. The project is running between 5-10 days behind schedule.

  4. The project is averaging a normal performance timeline.

Answer: C

Question No: 29

You are managing a project by using Project Professional 2013, and you notice a potential scheduling problem indicated by wavy red lines under some of the dates in the Finish column.

You need to resolve the issue. What should you do?

  1. Recalculate the project schedule.

  2. Adjust the resource assignment on the task to when the resource is available.

  3. Activate Task Inspector for the task to decide if adjustments are necessary.

  4. Adjust the finish date on the task to a date in the future.

Answer: C

Question No: 30

You are a program manager. Your project managers use Project Professional 2013 to manage projects. The project managers want to utilize the same resources across their projects.

You need to combine the projects, as well as the project resources, to see allocations across the projects.

What should you do?

  1. Copy and paste all resource assignments into a Master file.

  2. Share resources from an external resource pool.

  3. Create a Master project and insert subprojects by using Link to project.

  4. Open all projects in a new window.

Answer: B

100% Free Download!
Download Free Demo:74-697 Demo PDF
100% Pass Guaranteed!
Download 2017 EnsurePass 74-697 Full Exam PDF and VCE

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 EnsurePass IT Certification PDF and VCE

[Free] 2017(Sep) EnsurePass Testking Microsoft 74-697 Dumps with VCE and PDF 11-20

EnsurePass
2017 Sep Microsoft Official New Released 74-697
100% Free Download! 100% Pass Guaranteed!
http://www.EnsurePass.com/74-697.html

Managing Projects with Microsoft Project 2013

Question No: 11

You are a project manager who uses Project Professional 2013.

You manage a software development project and have baselined the project. Your Project Management Office (PMO) requires you to capture the actual hours per resource for each task in your project schedule. You use these weekly actual hours to generate a weekly report for your project sponsor.

Your resources report their actual hours each Friday.

You need to enter the hours in your Project Schedule on a weekly basis. What should you do?

  1. Choose Resource Usage view, add an Actual Work row, and enter total weekly hours per assignment in the appropriate week.

  2. Display the Team Planner view, add an Actual Work column, and enter total weekly hours for each task.

  3. Choose Gantt Chart view, add a Work column, and enter total weekly hours for each task.

  4. Choose Resource Form view, right-click to view Work Details, and enter total weekly

hours for each task.

Answer: A

Question No: 12

You are a project manager who uses Project Standard 2013.

A colleague sends you a Microsoft Excel file that contains a list of tasks that define a project you must complete.

You need to create a project file that contains this task list, ensuring that any fields are mapped correctly.

What should you do?

  1. Add the Import Project Wizard to the Quick Access Toolbar. Initiate the wizard and select the Excel file to import.

  2. Open the file in Excel, and copy and paste the tasks into a new project.

  3. Rename the Excel file to tasks.mpp and open the plan in Project Standard 2013.

  4. Open the Excel file by using Project Standard 2013 and import the task list using the Project Import Wizard.

Answer: D

Question No: 13

You are a resource manager who uses Project Standard 2013.

You manage all of your resources in a single plan, which acts as a Shared Resource Pool for other projects in your organization. Each resource needs to pass an annual exam in order to work on construction sites.

You need to set up a method that allows you to pick the renewal month for each resource. What should you do?

  1. Rename the Resource Text1 Custom field to Exam Expiration Date. Enter the month when the exam expires. Select the correct expiration date for each resource.

  2. Use the Organizer to copy the Resource Finish1 Custom field from the Global.mpt. Select the correct expiration date for each resource.

  3. Rename the Resource Date1 Custom field to Exam Expiration Date. Create a Lookup table with values containing the last date of each month. Select the correct expiration date for each exam.

  4. Rename the Resource Month1 Custom field to Exam Expiration Date. Create a Lookup table with monthly values. Select the correct expiration month for each exam.

  5. Rename the Resource Flag1 Custom field to Exam Expired Date. Enter the expiration dates into a Lookup table. Select the correct expiration date for each resource.

Answer: C

Question No: 14

You manage a project by using Project Professional 2013.

The Indicators column in the Gantt Chart view shows that there are overallocated resources for a task. A resource is assigned to multiple tasks at 100% on a specific day, totaling 2.5 hours of work for the day. The resource has availability of 8 hours for the day.

You need to solve this problem. What should you add to the task?

  1. A deadline

  2. A Finish to Start relationship

  3. A Finish to Finish relationship

  4. More work

Answer: B

Question No: 15

You use Project Professional 2013 to manage a project that has customer-required milestone completion dates.

You need to see graphically that your milestones have slipped beyond your customer- required dates.

What should you add to the project milestones?

  1. a Must finish on constraint

  2. a finish date

  3. a deadline

  4. a Finish no later than constraint

Answer: C

Question No: 16

You manage a project by using Project Professional 2013.

A critical task is out of scope for the project. The stakeholders suggest that the task be removed from the project but kept in the plan in case the task is needed in the future.

You need to implement a solution to meet the stakeholder#39;s request. What should you do?

  1. Click on the task, and click Inactivate.

  2. Move the task to after the ending date for the project.

  3. Delete the task from the schedule.

  4. Click the Unlink Task button to unlink the predecessors and successors for the task.

Answer: A

Question No: 17

You are an independent project manager who uses Project Professional 2013.

You work on multiple projects for different customers and use only one project to manage their tasks. You invoice your customers on a monthly basis. To identify tasks that have not been invoiced, you create a custom field called Not Invoiced.

Without losing the original project tasks#39; sort order, and without hiding any information, you need to see all tasks which have not been invoiced.

You create a custom filter based on the Not Invoiced custom field. What should you do next?

  1. Apply the custom filter.

  2. Export to Microsoft Excel using the custom filter.

  3. Apply the custom filter and select the Highlight option

  4. Use the filter in the Group By function.

Answer: C

Question No: 18

You are a project manager who uses Project Professional 2013.

A senior stakeholder asks you to update your project to reflect your organization#39;s scheduled two-week closure.

You need to reflect the closure within your schedule. What should you do?

  1. Create a resource and specify non-working days for the resource which reflect the closure. Assign this resource to each task.

  2. Open the Project Calendar and modify the default work week by setting the dates as non-working time.

  3. Create a new calendar and assign this to the tasks that are scheduled over the period of closure.

  4. Open the Project Calendar and enter the planned closure in the Exceptions tab.

Answer: D

Question No: 19

You are a project manager who uses Project Professional 2013.

Your organization migrates all project plans from Microsoft Excel to Project Professional 2013. One of the directors of the company has several years of experience using Excel Pivot Tables to analyze and make decisions about projects.

You need to enable project managers to view relevant project information in Excel Pivot Tables.

What should you do?

  1. Create a Report view by using the new Built-in Dashboards and Reports feature and export to Excel.

  2. Download and install the Microsoft Project to Pivot Table Tool and generate a new Excel Pivot Table by selecting the current project.

  3. Use the Excel Data From Other Sources feature to access your project file.

  4. Create a report by using the Visual Reports feature. Select Microsoft Excel and choose relevant data to view in the report.

Answer: D

Question No: 20

You are a project manager who uses Project Standard 2013.

You work on a project that requires you to generate many documents. Each task in your project plan must have a document associated and stored in your Microsoft SharePoint Intranet Environment. These documents are 25 megabytes in size.

You need to share this project plan by email with your team and ensure that they can easily access the documents.

What should you do?

  1. In the Task Information notes, insert an object from a file. Uncheck the Link option and make sure that it is a document, not a link. Select your document and click on it. Project will automatically create the reference to this document.

  2. Create a task custom field named Link to Document, and select the field type as Text Hyperlink. Copy the SharePoint URL of each document and paste it as a text into the Link to Document task custom field. Project Standard 2013 will convert this text to a clickable

    hyperlink.

  3. Copy and paste the document into your Gantt chart, and create a link between your task and the document.

  4. Go to backstage and use the feature Add and Link a SharePoint Document to My Tasks to select your document in your SharePoint Library. Select your task. Project will automatically create a clickable hyperlink.

  5. Copy the SharePoint URL of each document and paste in the Hyperlink task standard field as a text. Project will convert this text to a clickable hyperlink.

Answer: E

100% Free Download!
Download Free Demo:74-697 Demo PDF
100% Pass Guaranteed!
Download 2017 EnsurePass 74-697 Full Exam PDF and VCE

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 EnsurePass IT Certification PDF and VCE

[Free] 2017(Sep) EnsurePass Testking Microsoft 74-697 Dumps with VCE and PDF 1-10

EnsurePass
2017 Sep Microsoft Official New Released 74-697
100% Free Download! 100% Pass Guaranteed!
http://www.EnsurePass.com/74-697.html

Managing Projects with Microsoft Project 2013

Question No: 1

You are a project manager for a company that uses Project Professional 2013.

You are responsible for communicating the progress of your projects every month. Your company provides you with a Gantt Chart view that uses the standard Entry table.

You need to communicate the progress of tasks that have a finish date of either October 2 or October 22.

What should you do?

  1. Go to the Task tab, open the Find window, and set the parameters to find the required dates, setting the Look in Field to Finish. Then click Find Next.

  2. Go to the View tab, open the More Views window, and create a new view.

  3. Go to the View tab and use the Date Range filter.

  4. Go to the View tab and select Display AutoFilter. Click on the arrow next to the Finish column and check only the required dates.

Answer: D

Question No: 2

You are a project manager who uses Project Standard 2013.

Your current project has resources with the standard calendar as the base calendar. Some tasks of the project need to be done overnight so the night shift calendar is assigned to those tasks. When you assign a resource to one of these tasks, you get an error.

You need to correctly assign the resource. What should you do?

  1. Remove the night calendar from the task and re-assign the resource.

  2. Change the task mode to Manually Scheduled.

  3. Change the task type to Fixed Units, Effort Driven, and then re-assign the resource.

  4. Select scheduling ignores resource calendars for the task.

Answer: D

Question No: 3

You are a project manager for an organization that uses Project Professional 2013.

You are planning a project schedule that starts on March 1 and lasts four months. However, the sponsor now asks that the project be delayed to have a finish date of December 31.

  1. Change all task constraint types to Start no later than.

  2. Change the Schedule from field to Project Finish Date.

  3. Change the project Start date so that the project will finish on December 31.

  4. Change all task constraint types to As late as possible.

  5. Change the project Finish date so that the project will finish on December 31.

Answer: B,D,E

Question No: 4

You are a project manager who uses Project Professional 2013. You have worked on a project for four years and have created a very detailed project plan in Project Professional 2013. You use milestones as key deliverables, and you use summary tasks as phases.

Your company requests a presentation of the key deliverables for each phase of your project plan in a simple and consolidated view that fits in one Microsoft PowerPoint slide.

You need to ensure that phases and key deliverables are clearly shown in the timeline and are not confusing to the audience.

What should you do?

  1. Create a new Timeline view from existing tasks in your project plan. Drag the timeline into a blank PowerPoint slide.

  2. Create a new Timeline view that automatically shows milestones for each stage of your project. Copy the full-size timeline and paste to your PowerPoint slide.

  3. Add all summary tasks to your timeline. Project Professional 2013 will automatically recognize and add all milestones on each stage to your Timeline view. Copy the full-size timeline and paste to the PowerPoint slide.

  4. Add all summary tasks to your timeline. Add all milestones to your timeline. Copy the full-size timeline and paste to your PowerPoint slide.

Answer: D

Question No: 5 DRAG DROP

You are a project manager who uses Microsoft Project 2013.

A resource manager notifies you that your assigned resource is now only available 50% to work on the communication plan task. The estimated amount of work for the task remains the same at 16 hours. The task must also be completed within the original two-day commitment even though the resource is only available 50% of the time.

You need to bring on another resource to assist with the remaining 50% of the work while ensuring that the same amount of work gets done in the two days that were originally committed.

Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.)

Ensurepass 2017 PDF and VCE

Answer:

Ensurepass 2017 PDF and VCE

Explanation:

Box 1: Assign the additional resource to the task. Box 2: Set the task type to fixed work,

Box 3: Change both the new and existing resource units to 50%.

Note:

* For a fixed-work task

/ You can change the assignment units value and Project will recalculate the duration.

/ You can change the duration value and Project will recalculate peak units per time period. The assignment units value is not affected.

Question No: 6

You are a project manager who uses Project Professional 2013.

After updating a project schedule, you want to determine the amount of time that the schedule has slipped from the original scheduled dates.

You need a graphical view that shows the current schedule to baseline. Which view should you use?

  1. Detail Gantt view

  2. Tracking Gantt view

  3. Leveling Gantt view

  4. Gantt Chart view

Answer: B

Question No: 7

Your company uses Project Professional 2013.

You are building a schedule by using predecessors to help determine a logical duration. The following image shows a baselined list of tasks with predecessors:

Ensurepass 2017 PDF and VCE

You have been told that Task C is optional, and you recommend inactivating the task to keep it visible on the schedule.

You need to determine what the results are to the schedule when inactivating Task C. How should you answer?

  1. The finish date is reduced by four working days, cost remains unchanged, and baseline cost is reduced by $400.

  2. The finish date is reduced by five working days, cost remains unchanged, and baseline cost is unchanged.

  3. The finish date is reduced by six working days, cost is reduced by $400, and baseline cost is reduced by $400.

  4. The finish date is reduced by four calendar days, cost is reduced by $400, and baseline cost is reduced by $400.

  5. The finish date is reduced by six calendar days, cost is reduced by $400, and baseline cost is unchanged.

Answer: E

Question No: 8

You are a project manager who uses Project Professional 2013.

You are creating a project with several phases. Your customer requires the delivery phase of the project to start on July 1 and to finish within four weeks. The delivery phase includes a summary task, which consists of five separate sub tasks.

You need to monitor this phase closely to ensure that it does not overrun.

What should you do?

  1. Create an automatically scheduled summary task of 20 days. Set the finish date to July 29.

  2. Create a manually scheduled summary task of 20 days. Enter a Finish No Later Than constraint which is set to July 29.

  3. Create a manually scheduled summary task of 20 days. Create a deadline for the task which is set to July 29. Monitor the progress of the summary task against the deadline.

  4. Create an automatically scheduled summary task of 20 days. Set the start date to July 1.

  5. Set a deadline date for the automatically scheduled summary task for four weeks after July 1. Monitor the progress of the summary task against the deadline.

Answer: E

Question No: 9

You are a project manager for a large telecommunications company that uses Project Professional 2013.

The project you have been assigned has a fixed cost of 5150,000. The fixed cost is for the entire project and not for an individual task.

You need to add the fixed cost of S 150,000 to your schedule and spread it across the duration of the project.

What should you do?

  1. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task 0. Change Fixed Cost Accrual to Start.

  2. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task 0. Change Fixed Cost Accrual to Prorated.

  3. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task 0. Change Fixed Cost Accrual to End.

  4. In the Gantt chart, change Table view to Cost, and enter $150,000 in the Fixed Cost field for Task 1. Change Fixed Cost Accrual to Start.

Answer: B

Question No: 10

Your company uses Project Professional 2013, and you are setting up an initial planning schedule.

You need to set each task duration as estimated, until the estimate is confirmed by the assigned resource.

What should you do?

  1. Select the estimated check box.

  2. Use a task custom field and set the Roll task down to assignment check box.

  3. Enter the duration suffixed with -ed for estimated days.

  4. Set the task to manually scheduled.

  5. Use an assignment custom field and set the Roll assignment up to task check box.

Answer: A

100% Free Download!
Download Free Demo:74-697 Demo PDF
100% Pass Guaranteed!
Download 2017 EnsurePass 74-697 Full Exam PDF and VCE

EnsurePass ExamCollection Testking
Lowest Price Guarantee Yes No No
Up-to-Dated Yes No No
Real Questions Yes No No
Explanation Yes No No
PDF VCE Yes No No
Free VCE Simulator Yes No No
Instant Download Yes No No

2017 EnsurePass IT Certification PDF and VCE

[Free] 2017(Sep) EnsurePass Testinsides Microsoft 74-697 Dumps with VCE and PDF 51-60

EnsurePass
2017 Sep Microsoft Official New Released 74-697
100% Free Download! 100% Pass Guaranteed!
http://www.EnsurePass.com/74-697.html

OEM Preinstallation

Question No: 51

You plan to deploy several servers that have 3-TB hard disks.

You need to verify whether the servers can support system volumes that are larger than 2 TB.

Which hardware feature should you verify is available on the servers?

  1. Unified Extensible Firmware Interface (UEFI)

  2. Extended Industry Standard Architecture (EISA)

  3. Universal Disk Format (UDF)

  4. BIOS Enhanced Disk Drive Services

Answer: A

Question No: 52

You deploy a Windows 8 image to a reference computer.

You sign in to the reference computer by using the built-in administrator account and you modify the user environment.

You need to deploy the image to several client computers. The image must contain the profile of the built-in administrator account as the default user profile.

Which two actions should you perform before you capture the image? (Each correct answer presents part of the solution. Choose two.)

  1. Create an answer file that contains the Microsoft-Windows-Shell-Setup settings.

  2. Run dism.exe /image.

  3. Run sysprep.exe /generalize /mode:vm.

  4. Run dism.exe /apply-unattend:unattend.xml.

  5. Create an answer file that contains the Microsoft-Windows-Setup\UserData settings.

  6. Run sysprep.exe /audit /unattend:unattend.xml.

  7. Run sysprep.exe /generalize/unattend:unattend.xml.

Answer: E,G

Explanation: E:Use the following procedure (not displayed below) to create an answer file to instruct Sysprep to copy user profile settings when you generalize the Windows image.

  • (G) On the reference computer, open an elevated command prompt, and then type this command:

  • C:\Windows\System32\Sysprep\Sysprep /generalize /oobe /shutdown /unattend:

    F:\CopyProfile.xml

    where F is the letter of the USB flash drive or other removable media. The Sysprep tool removes computer-specific information from the image, while preserving the user profile

    settings that you configured.

    Note:

    You can use the CopyProfile setting to customize a user profile and then copy that profile to the default user profile. Windows庐 uses the default user profile as a template to assign a profile to each new user. By customizing the default user profile, you can configure settings for all user accounts that are created on the computer. By using CopyProfile, you can customize installed applications, drivers, desktop backgrounds, internet explorer settings, and other configurations. Note that some settings are not preserved by using CopyProfile.

    Reference:Customize the Default User Profile by Using CopyProfile

    Question No: 53

    Your company#39;s deployment environment contains the following:

    ->One subnet

    ->One Active Directory domain

    ->Two servers that run Windows Server 2012

    You need to recommend a solution to deploy an image to at least 100 client computers simultaneously.

    The solution must start deploying the image automatically when 20 client computers are available to receive the image.

    What should you include in the recommendation?

    1. The Multipath I/O (MPIO) feature and the File Server role

    2. The Windows Deployment Services server role that contains a Scheduled-Cast transmission

    3. The Windows Deployment Services server role that contains an Auto-Cast transmission

    4. The Scale-Out File Server for application data role and the Reliable Multicast Protocol

    Answer: B

    Question No: 54

    You work for an OEM system builder.

    A technician applies a generalized image of Windows 8 to a client computer, and then shuts down the computer.

    You need to configure the computer for push-button reset. What should you do first?

    1. Start the computer from Windows Preinstallation Environment (Windows PE), and then run sysprep.exe /oobe.

    2. Start the computer, and then complete the installation of Windows 8.

    3. Start the computer, and then shut down the computer when Windows Welcome appears.

    4. Start the computer from Windows Preinstallation Environment (Windows PE), and then run wbadmin.exe.

    Answer: C

    Question No: 55

    You have a Windows 8 image.

    You plan to deploy the image to several client computers. The client computers will be delivered to several different customers.

    You plan to provide all of the customers with the ability to perform a push-button reset of their computers from recovery media. The push-button reset will include a script that will repartition the hard disk drives automatically.

    You need to identify which encoding format must be used for the script file. Which encoding format should you identify?

    1. Unicode

    2. BigEndianUnicode

    3. ANSI

    4. UTF-8

    Answer: D

    Question No: 56

    You work for an OEM system builder.

    You have a reference computer that runs Windows 8. You plan to create an image of the computer.

    You need to ensure that when the image is deployed to a computer, a custom application is installed in audit mode the first time the computer starts.

    What should you do before you capture an image of the reference computer?

    1. Create an answer file that contains a FirstLogonCommands object. Run sysprep /audit

      /generalize /shutdown.

    2. Create an answer file that contains a FirstLogonCommands object. Run sysprep /oobe

      /generalize /shutdown.

    3. Create an answer file that contains a RunSynchronous object. Run sysprep /audit

      /generalize /shutdown.

    4. Create an answer file that contains a RunSynchronous object. Run sysprep /oobe

    /generalize /shutdown.

    Answer: C

    Question No: 57

    Which statement correctly describes the functionality of the Windows 8 version of Reagentc?

    1. Reagentc can be used to service an online image and an offline image.

    2. Reagentc can be used to service an online image only.

    3. Reagentc can be used to service an offline image only.

    4. Reagentc can be used from Windows Preinstallation Environment (Windows PE) only.

    Answer: A

    Question No: 58

    You use online servicing to preinstall Skype in a Windows 8 image.

    When you deploy and test the image, the Skype tile is not displayed on the Start screen.

    You need to ensure that the Skype tile is displayed on the Start screen after the Out-of-Box Experience (OOBE) completes.

    What should you do?

    1. Run dism.exe and specify the /Enable-Feature parameter.

    2. Run dism.exe and specify the /Add-ProvisionedAppxPackage parameter.

    3. Add the shortcut path to the Unattend.xml file by using the AppIdOrPath property.

    4. Place a shortcut in %ALLUSERSPROFILE%\Microsoft\Windows\Start Menu\Programs.

    Answer: C

    Question No: 59

    You plan to capture a Windows 8 reference installation. The reference installation contains several third-party drivers for USB devices.

    You need to ensure that the third-party device drivers are preserved in the captured Windows image.

    Which component should you configure in the answer file?

    1. Microsoft-Windows-PnpCustomizationsNonWinPE

    2. Microsoft-Windows-Setup

    3. Microsoft-Windows-Deployment

    4. Microsoft-Windows-PnpSysprep

    Answer: D

    Question No: 60

    You have a client computer that runs Windows 8 and has the Windows Assessment and Deployment Kit (Windows ADK) installed.

    You need to create a Windows Preinstallation Environment (Windows PE) build environment.

    Which command should you use?

    1. copype.cmd

    2. wpeinit.exe

    3. makewinpemedia.cmd

    4. wpeutil.exe

    Answer: A

    100% Free Download!
    Download Free Demo:74-697 Demo PDF
    100% Pass Guaranteed!
    Download 2017 EnsurePass 74-697 Full Exam PDF and VCE

    EnsurePass ExamCollection Testking
    Lowest Price Guarantee Yes No No
    Up-to-Dated Yes No No
    Real Questions Yes No No
    Explanation Yes No No
    PDF VCE Yes No No
    Free VCE Simulator Yes No No
    Instant Download Yes No No

    2017 EnsurePass IT Certification PDF and VCE

    [Free] 2017(Sep) EnsurePass Testinsides Microsoft 74-697 Dumps with VCE and PDF 41-50

    EnsurePass
    2017 Sep Microsoft Official New Released 74-697
    100% Free Download! 100% Pass Guaranteed!
    http://www.EnsurePass.com/74-697.html

    OEM Preinstallation

    Question No: 41

    You have a server namedServer1.Server1is the member of a workgroup.

    OnServer1, you create a local user account namedUser1, as shown in the following exhibit. (Click the Exhibit button.)

    Ensurepass 2017 PDF and VCE

    OnServer1, you create a share namedShare1. You assignUser1Full control permissions toShare1. You copy the source files for Windows 8 toShare1.

    When attempting to accessShare1from Windows Preinstallation Environment (Windows PE),User1receives an error message.

    You need to ensure thatUser1can accessShare1from Windows PE. What should you do?

    1. From Server1, modify the Advanced Sharing properties.

    2. Clear the Password never expires check box for the user account of User1.

    3. Add a password to the user account of User1.

    4. From Server1, modify the Advanced settings in System Properties.

    Answer: C

    Question No: 42

    You have a server named Server1that runs Windows Server 2012 and has the Windows Deployment Services server role installed.

    You recently removed a third-party DHCP server from the network, and then installed the DHCP Server server role onServer1.

    You create a scope onServer1.

    You discover that client computers attempting to receive a Windows 8 image fail to connect toServer1.

    You verify that the client computers on the network can receive an IP address fromServer1.

    You need to ensure that the computers attempting to receive an image can connect toServer1.

    Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)

    1. From the DHCP console, click Server Options, and then set the value of Option 66 to Server1.

    2. From the Windows Deployment Services console, click the PXE Response tab, and then set the value of the Delay in seconds to 3.

    3. From the Windows Deployment Services console, click the DHCP tab, and then select the Do not listen on port 67 check box.

    4. From the DHCP console, click Server Options, and then set the value of Option 67 to install.wim.

    5. From the Windows Deployment Services console, click the DHCP tab, and then select the Configure DHCP option 60 to indicate that this is also a PXE server check box.

    Answer: C,E

    Explanation: If DHCP and WDS roles are installed on same server – In this case you must tell WDS not to listen on port 67 and set DHCP option 60 so that clients can find the WDS server. So options Do not listen on port 67 (C) and Configure DHCP option 60 to indicate that this server is also a PXE server (E) must be checked.

    Ensurepass 2017 PDF and VCE

    Deploying Windows 7 Using Windows Deployment Services Snap 1 Reference:Deploying Windows 7 Using Windows Deployment Services

    Question No: 43

    You plan to deploy multiple client computers that will each contain a 4-TB hard disk drive. The hard disk drives will be initialized as GPT drives.

    You need to identify the maximum number of primary partitions that can be created on a GPT drive.

    How many primary partitions should you identify?

    1. 4

    2. 64 C. 128 D. 256

    Answer: C

    Question No: 44

    You create and deploy an image to a reference computer. You plan to deploy the image to several client computers.

    You need to meet the following requirements for the planned deployment:

    ->Remove all of the unique system information from the image.

    ->Display the Windows Welcome screen the first time a new computer starts.

    Which command should you run?

    1. sysprep /audit /generalize /reboot

    2. sysprep /oobe /generalize /shutdown

    3. sysprep /audit /oobe /generalize

    4. sysprep /generalize /quiet /reboot

    Answer: B

    Question No: 45

    You work for an OEM system builder named Fabnkam, Inc.

    Fabrikam sells personal computers that have Windows 8 preinstalled.

    You need to recommend a recovery solution that provides customers with the ability to repair their computers quickly, while preserving data and important customizations. The solution must not back up data in advance and must comply with the Microsoft OEM system builder license.

    What should you recommend?

    1. Windows Backup

    2. File History

    3. Push-button reset

    4. The Microsoft Diagnostics and Recovery Toolset (DaRT)

    Answer: C

    Question No: 46

    You work for an OEM system builder.

    What are three possible ways to distribute Windows 8 OEM desktop operating system licenses? (Each correct answer presents a complete solution. Choose three.)

    1. Asealed System Builder pack that comes with the purchase of a new computer that has an operating system preinstalled

    2. Asealed System Builder pack without the purchase of a computer

    3. Asealed System Builder pack that comes with the purchase of a new computer that does not have an operating system preinstalled

    4. An unsealed System Builder pack without the purchase of a computer

    5. An unsealed System Builder pack that comes with the purchase of a new computer that does not have an operating system preinstalled

    6. An unsealed System Builder pack that comes with the purchase of a new computer that has an operating system preinstalled

    Answer: A,C,E

    Explanation: Windows 8 licensing terms for OEM system builder packs

  • (F) Opened pack

    By opening the pack, you agree to the license terms. You must preinstall the license for Windows desktop software onto a fully assembled PC#39;s hard drive using the OPK.

  • Unopened pack

    Unopened packs can be delivered to another system builder-an OEM, assembler, refurbisher, or preinstaller of software on computer systems.

    Question No: 47

    Your company plans to implement a deployment solution for 500 new client computers. The company identifies the following requirements for the planned implementation:

    ->A technician must be able to deploy operating systems to computers that use the ARM architecture.

    ->The solution must NOT require the implementation of an Active Directory forest.

    ->A technician must be able to schedule the deployment of operating systems.

    You need to recommend a solution that meets the requirements.

    Which two technologies should you include in the recommendation? (Each correct answer presents part of the solution. Choose two.)

    1. Windows Server 2012 Standard

    2. Windows Deployment Services (WDS)

    3. The Microsoft Deployment Toolkit (MDT)

    4. Windows Server 2008 R2 Enterprise

    5. Microsoft System Center 2012

    6. Windows Server 2008 R2 Standard

    Answer: A,B

    Explanation: WDS can now(windows Server 2012)deploy images to ARM clients, which is

    a CPU architecture that is specially engineered for low-cost, low-power consumption devices such as tablets, cell phones, GPS units, portable game consoles, network routers, and media players.

    Incorrect:

    Not C:MDT does not support ARM processor-based versions of Windows. Reference:What#39;s New for Windows Deployment Services for Windows Server 2012

    Question No: 48

    You work for an OEMsystem builder named Fabrikam,Inc.

    You use Windows Deployment Services (WDS) to start bare metal deployments that use Pre-Boot Execution Environment (PXE) and a 32-bit boot image. The boot image starts to a command prompt and automatically establishes a network connection.

    You plan to create a reference image of the 64-bit version of Windows 8 Pro.

    From the distribution share, you execute Windows Setup from the Windows 8 Pro 64-btt source files and you receive an error message indicating that Windows Setup is incompatible with the version of Windows that you are running.

    You need to ensure that you can create the reference image. What should you do?

    1. Configure the BIOS to use Unified Extensible Firmware Interface (UEFI) mode.

    2. Run setup.exe and specify the /InstallFrom parameter.

    3. Create a boot image that contains a 64-bit version of Windows Preinstallation Environment (Windows PE).

    4. Specify the MetaData setting in an answer file.

    Answer: C

    Question No: 49

    You work for an OEM system builder named Fabrikam, Inc.

    You plan to deploy Windows by running setup.exe and an answer file. You need to configure the answer file to perform the following:

    ->Install an out-of-box device driver.

    ->Set the path to the out-of-box device driver to a network share.

    Which two possible configuration passes can you use to achieve this goal? (Each correct answer presents a complete solution. Choose two.)

    1. Specialize

    2. Generalize

    3. OfflineServicing

    4. WindowsPE

    Answer: C,D

    Explanation: You can install additional device drivers during Windows Setup by creating an answer file. In this answer file, you can specify the paths to device drivers on a network share (or a local path) by adding the Microsoft-Windows-PnpCustomizationWinPE or Microsoft-Windows-PnpCustomizationNonWinPE components and specifying the configuration passes in which you intend to install them. You can install device drivers in the windowsPE (D), offlineServicing (C), auditUser or auditSystem configuration passes.

    Reference:Add Device Drivers During Windows Setup

    Question No: 50

    You have 3 reference computer that runs the English version of Windows 7 Ultimate.

    You plan to provide customers with the ability to switch between an English user interface (UI) and a German UI in Windows 7.

    You start the reference computer in audit mode.

    You need to add the German language pack to the reference computer.

    Which two possible tools can you use to achieve this goal? (Each correct answer presents a complete solution. Choose two.)

    1. Computer Management

    2. System in Control Panel

    3. Windows Update

    4. Region and Language in Control Panel

    5. Programs and Features in Control Panel

      Answer: C,D

      Explanation: C: In Windows 7, you can download languages in two ways:

  • Using Windows Update. If you#39;re running an Ultimate or Enterprise edition of Windows, you can download available language packs by using Windows Update. Language packs installed using Windows Update provide a fully translated version of Windows dialog boxes, menu items, and help content. All the languages available for this type of download have a quot;Learn howquot; link in the right column of the table below.

    *Using Microsoft Download Center. You can download Language Interface Packs (LIPs) from the Microsoft Download Center by using the links below.

    C,D: Install a Language Pack (LIP)

      1. Open the Control Panel (icon view), and click on the Windows Update icon. OR

      2. Open the Control Panel (icon view), and click on the Region and Language icon. Click on the Keyboards and Languages tab, then click on the Install/uninstall languages button.

        100% Free Download!
        Download Free Demo:74-697 Demo PDF
        100% Pass Guaranteed!
        Download 2017 EnsurePass 74-697 Full Exam PDF and VCE

        EnsurePass ExamCollection Testking
        Lowest Price Guarantee Yes No No
        Up-to-Dated Yes No No
        Real Questions Yes No No
        Explanation Yes No No
        PDF VCE Yes No No
        Free VCE Simulator Yes No No
        Instant Download Yes No No

        2017 EnsurePass IT Certification PDF and VCE

  • [Free] 2017(Sep) EnsurePass Testinsides Microsoft 74-697 Dumps with VCE and PDF 31-40

    EnsurePass
    2017 Sep Microsoft Official New Released 74-697
    100% Free Download! 100% Pass Guaranteed!
    http://www.EnsurePass.com/74-697.html

    OEM Preinstallation

    Question No: 31

    You have a Windows Recovery Environment (Windows RE) image named Winre.wim. You need to enable support for HTML applications in the image.

    Which tool should you use?

    1. Winrecfg

    2. Reagentc

    3. Sysprep

    4. Dtsm

    Answer: A

    Question No: 32

    You have a Windows 8 image.

    You are testing the Out-of-Box-Experience (OOBE).

    You discover that when neither a keyboard nor a mouse is connected, the Human Interface Device (HID) pairing instructions do not appear.

    You need to ensure that the HID pairing instructions appear when the image starts on a client computer that has neither a keyboard nor a mouse connected.

    Which file should you create?

    1. unattend.xml

    2. Oobe.xml

    3. Coconfig.xml

    4. Sysprep.inf

    Answer: B

    Question No: 33

    You start a computer namedComputer1from Windows Preinstallation Environment

    (Windows PE).

    You discover that you cannot access the network because the driver for the network card is not included in Windows PE.

    You obtain a valid network driver forComputer1.

    You need to ensure that you can access the network fromComputer1immediately. What should you do?

    1. Run dism.exe and specify the /Add-Driver parameter and the INF file of the driver.

    2. Run pnputil.exe and specify the -a parameter and the folder where the driver is located.

    3. Run drvload.exe and specify the INF file of the driver.

    4. Run wpeutil.exe and specify the InitializeNetwork parameter and the folder where the driver is located.

    Answer: C

    Question No: 34

    You use Windows Deployment Services (WDS) to deploy Windows operating system images.

    You create a custom image of Windows Preinstallation Environment (Windows PE).

    You need to ensure that client computers use Pre-Boot Execution Environment (PXE) to load the Windows PE image.

    To which node in the Windows Deployment Services console should you add the image?

    1. Install Images

    2. Multicast Transmissions

    3. Boot Images

    4. Pending Devices

    5. Legacy Images

    Answer: C

    Question No: 35

    You work for an OEM system builder.

    You deploy Windows 8 to a client computer that has a 64 GB-Solid State Drive (SSD) by using a configuration set from a USB key.

    You need to reduce the size of the Windows installation as much as possible. Which folder should you remove from the installation?

    1. %WINDIR%\Panther

    2. %WINDIR%\Addins

    3. %WINDIR%\Configsetroot

    4. %WINDIR%\Branding

    Answer: C

    Question No: 36 DRAG DROP

    Your network contains an Active Directory domain named contoso.com and a DHCP server named DHCP1.

    You have a technician computer that has the Windows Assessment and Deployment Kit (Windows ADK) installed.

    You prepare a reference computer namedComputer1.

    You install Windows Deployment Services (WDS) on a server namedServer1. You need to capture an image ofComputer1and store the image onServer1.

    Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.)

    Ensurepass 2017 PDF and VCE

    Answer:

    Ensurepass 2017 PDF and VCE

    Explanation:

    Box 1:Create a capture image.

    Box 2:Start Computer1 by using Pre-Boot Execution Environment (PXE). Box 3:Add an install image to WDS.

    Note:

    Box 1: A capture image is created from an existing boot image. You will create a new capture image by right-clicking on an existing boot image and then selecting Create Capture Image option. The Create Capture Image Wizard will start.

    Box 2:How to Create An Image by Using a Capture Image

    Power up the reference machine and boot it up on the network. Choose the capture boot image when the PXE client starts.

    Box 3:

    The boot image will download over the network and start. A wizard starts. Later in the Wizard:

    Ensurepass 2017 PDF and VCE

    Question No: 37

    You need to prepare a hard disk for a Unified Extensible Firmware Interface (UEFI)-based computer.

    Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)

    1. Covert the hard disk to a GPT disk.

    2. Format the Windows partition by using NTFS.

    3. Format the Windows partition by using FAT32.

    4. Create an EFI partition.

    5. Mark the system partition as active.

    Answer: A,B,D

    Explanation: A:The GUID Partition Table (GPT) was introduced as part of the Unified Extensible Firmware Interface (UEFI) initiative. GPT provides a more flexible mechanism for partitioning disks than the older Master Boot Record (MBR) partitioning scheme that was common to PCs.

    B: NTFS is the best choice for the Windows partition.

    D:The EFI System partition is formatted using the FAT12, FAT16 or FAT32 file system.

    Question No: 38

    You are an OEM system builder.

    You are customizing the OEM support information for Windows 8. You set HelpCustomized to true.

    You need to identify where the customized support information will appear. What should you identify?

    1. System in Control Panel

    2. Windows Help and Support

    3. The Windows Welcome screen

    4. Troubleshooting in Control Panel

    Answer: B

    Question No: 39

    You have three images sealed in Out-of-Box-Experience (OOBE) mode. You use the images on a daily basis to build client computers for customers.

    A new customer places an order for 500 computers. The customer#39;s requirements for the computers are not met by any of the images.

    You identify an image that you can modify by installing two applications required by the customer.

    You plan to customize the image before you deploy the image to the computers. You need to identify which steps must be taken to modify the image.

    What should you do before you capture the image?

    1. Start the image in audit mode on a reference computer. Install the required applications. Seal the image in audit mode.

    2. Start the image in audit mode on a reference computer. Install the required applications. Seal the image in OOBE mode.

    3. Start the image in audit mode on a reference computer. Install the required applications. Restart the computer.

    4. Start the image on a reference computer. Install the required applications. Seal the image in audit mode.

    Answer: B

    Question No: 40

    You are creating a Windows 8 answer file.

    You need to modify the order in which the app tiles appear on the Start screen.

    Which component should you add to the answer file?

    1. Microsoft-Windows-Deployment

    2. Microsoft-Windows-Setup

    3. Microsoft-Windows-SharedAccess

    4. Microsoft-Windows-Shell-Setup

    Answer: D

    100% Free Download!
    Download Free Demo:74-697 Demo PDF
    100% Pass Guaranteed!
    Download 2017 EnsurePass 74-697 Full Exam PDF and VCE

    EnsurePass ExamCollection Testking
    Lowest Price Guarantee Yes No No
    Up-to-Dated Yes No No
    Real Questions Yes No No
    Explanation Yes No No
    PDF VCE Yes No No
    Free VCE Simulator Yes No No
    Instant Download Yes No No

    2017 EnsurePass IT Certification PDF and VCE